2024 Improvement Project- Highland/Brown/Willow

Map

Project Timeline:

  • Engineer Report Presented to Council:  November 13, 2023
  • Project Open House:  November 29, 2023
  • Public Hearing/Council Authorizes Plans and Specifications:  December 11, 2023 
  • Council Approves Plans and Specs and Authorizes Advertisement of Bids: February 2024
  • Bids Received from Contractors:  March 2024
  • Award Contract: April 2024
  • Start of Construction: May 2024
  • Assessment Hearing: Fall of 2024
  • Substantial Completion Date:  October 2024 
  • Final Completion Date:  June 2025

**Updates on the project schedule will be updated periodically

Planned Improvements:

  • Street Reconstruction of Highland Street, Brown Avenue South, Willow Drive and Willow Circle
    • Total reconstruction of pavement section 
    • Concrete curb and gutter on all streets
    • Sidewalk constructed on the North side of Highland Street.
  • Sanitary Sewer Improvements
    • Lining sanitary sewer pipe in project area
    • New 4-inch sewer services
    • Lining and rehabilitation of sanitary sewer manholes
  • Watermain Improvements
    • New 8-inch watermain, gate valves, hydrants, and water services
  • Store Sewer Improvements
    • New Polyvinyl Chloride Pipe (PVC)
    • New concrete manholes
    • New PVC catch basins
    • New concrete curb and gutter

Project Contacts:

If you have any questions or concerns related to the project, you can reach out to the engineers listed below.  

Nick Peterson, Assistant City Engineer- (320) 905-9357 or by Email